Development of a catamaran prototype
Together with Globetter s.r.o., a Czech houseboat manufacturer, we participate in the development of a prototype vessel with a view of serial production.…
We prepared steel structures and railings for the new Stop Shop shopping park in Litvínov. The contract included the production, supply of material and assembly on site.
Execution
Preparation
The entire project began with focusing on the construction site, designing an appropriate procedure and individual elements. After the investor approved the project, several months of production began in the hall.
Assembly
Steel structures were transported to their destination and their assembly began using heavy equipment, platforms and assembly and welding workers.
Result
Further cooperation on smaller projects followed after successfully completing the contract.
Together with Globetter s.r.o., a Czech houseboat manufacturer, we participate in the development of a prototype vessel with a view of serial production.…
Serial production of guards for Weidemann GmhB, a leading manufacturer of work equipment in Germany, took place steadily from 2006 to…
We implement the Grammer Management System mobile app project (GMS Mobile) for maintenance workers. Customer profile Grammer CZ is a manufacturer…